MIL-PRF-83383E
TABLE III. Group A inspection.
Requirement
Method
Inspection
paragraph
paragraph
Group I
Visual and mechanical inspection:
Dimensions 1/
Workmanship
Dielectric withstanding voltage
Insulation resistance
Voltage drop
Group II
Visual and mechanical inspection:
Marking
Calibration
High temperature cycling 2/
1/ Dimensional measurements shall be made on two units only.
2/ If the contractor can demonstrate that this test has been performed for three consecutive periods
with zero failures, this test, with the approval of the qualifying activity, can be performed as part of
the Group B testing. This test to be performed prior to the dielectric withstanding voltage test in
table V.
TABLE IV. Group A, zero defect sampling plan.
Lot size
Sample size
100 percent
1 -
13
13
14 -
150
20
151 -
280
29
281 -
500
34
501 - 1,200
42
1,201 - 3,200
50
3,200 - 10,000
60
10,001 - 35,000
74
35,001 - 150,000
90
150,001 - 500,000
102
500,001 and up
12
For Parts Inquires submit RFQ to Parts Hangar, Inc.
© Copyright 2015 Integrated Publishing, Inc.
A Service Disabled Veteran Owned Small Business